Performance Dashboard (Real Time)

New Water Connection

PARTICULARS DETAIL TYPE
Total Number Of Applications Received 489
Total Number Of Application Approved 104
Average Time taken for Approval 728.0
Median Time taken for Approval 595.0
Minimum Time taken for Approval 4.0
Maximum Time taken for Approval 2304.0
* "Average Fee" for the water supply connection *Rs.11800/-
PARTICULARS DETAIL TYPE
Total Number Of Application Rejected 179
Average Time taken for Rejection 325.0
Median Time taken for Rejection 205.0
Minimum Time taken for Rejection 0.0
Maximum Time taken for Rejection 2158.0

Timeline for processing water supply connection application

Pre-feasibility report and to intimate the rough cost to the applicant 22 Days
Completion of DPR, clearance from regional and head office 80 Days
Concluding MoU between TWAD Board and the beneficiary 22 Days
Administrative and technical approval by TWAD Board 22 Days
Execution of works 66 Days to 264 Days

Name Change /name Transfer

PARTICULARS DETAIL TYPE
Total Number Of Applications Received 24
Total Number Of Application Approved 3
Average Time taken for Approval 154.0
Median Time taken for Approval 135.0
Minimum Time taken for Approval 131.0
Maximum Time taken for Approval 197.0
* "Average Fee" for the water supply connection *Rs.11800/-

Notes:-

* Water supply connection - Charges / Tariff