Timeline for processing water supply connection application
| Pre-feasibility report and to intimate the rough cost to the applicant | 22 Days |
| Completion of DPR, clearance from regional and head office | 80 Days |
| Concluding MoU between TWAD Board and the beneficiary | 22 Days |
| Administrative and technical approval by TWAD Board | 22 Days |
| Execution of works | 66 Days to 264 Days |